Project Update - 6/7/17

Four week look ahead - 

Week of 6/12-6/16:

  • M-Tue: Pour stamped section of sidewalks and base for cobblestones at 131 Rantoul St.
  • Tue-W: Pour remaining sidewalks at 131 Rantoul St.  
  • Th-F: Install cobblestone strips at 131 Rantoul St.  
  • Tue: Excavate and grade lot at Waters and Brown.
  • W: Pave top coarse on drives at Waters and Brown lot. 
  • M-Th: Plant tree along Phases 1, 2 and 3. 
  • M-F: Grade sidewalks and driveways in Phase 5 section. 
  • M-Tue: Install curb on Rantoul St at Elliott St intersection.
  • Th-F: Install signal wire and set mast arms in Phase 5 area.
  • M-W: Excavate sidewalks in Phase 6 section.
  • M-W: Install light foundations and conduit in Phase 5 section.
  • M-F: Install light conduit in Phase 6 section.
  • M-F: Excavate and pour mast arm foundations in Phase 6 section.
  • M-F: Roadway excavation and install gravel in Phase 7 section. 

Week of 6/19-6/23: 

  • Th: Remove hydrants at Wallis St and Federal St. 
  • M-F: Grade sidewalks and driveways in Phase 5 section. 
  • M-W: Install signal wire and set mast arms in Phase 5 area.
  • M-F: Pour sidewalks and driveways in Phase 5 section.
  • M-F: Install light conduit in Phase 6 section.
  • M-F: Install curb in Phase 6 section. 
  • M-F: Roadway excavation and install gravel in Phase 7 section.  
  • M-Th: Install regulatory signs in Phase 1, 2, 3, and 4A. 

Week of 6/26-6/30:

  • M-F: Pour sidewalks and driveways in Phase 5 section.
  • M-F: Install curb in Phase 6 section. 
  • M-Th: Fine grade and pave base and binder in Phase 7 section. 

Week of 7/3-7/7:

  • M: Pour sidewalks and driveways in Phase 5 section.