Project Update - 6/21/17

Four week look ahead - 

Week of 6/26-6/30:

  • M-F: Pour sidewalks and driveways in Phase 5 section.
  • M-F: Pave binder in driveways in Phase 5 section. 
  • W-F: Set light poles in Phase 5 section.
  • M-F: Install light conduit in Phase 6 section.
  • M-F: Install curb in Phase 6 section. 
  • Tue-F: Grade sidewalks and drives in Phase 6 section. 
  • M-Th: Fine grade and pave base and binder in Phase 7 section. 

Week of 7/3-7/7: 

  • M: Pour sidewalks and driveways in Phase 5 section.
  • M: Pave binder in driveways in Phase 5 section. 
  • M-Tue: Set light poles in Phase 5 section.
  • M-F: Install light conduit in Phase 6 section.
  • M-F: Grade sidewalks and drives in Phase 6 section. 

Week of 7/10-7/14:

  • M-Tue: Set billboard support system at Gloucester Crossing. 
  • M-Tue: Plant remaining trees within Phases 1-4. 
  • M: Install light conduit in Phase 6 section.
  • M-F: Grade sidewalks and drives in Phase 6 section. 
  • M-F: Excavate and pour mast arm foundations in Phase 7 section.
  • M-Th: Install regulatory signs in Phase 1, 2, 3, and 4A.  

Week of 7/17-7/21:

  • M-F: Grade sidewalks and drives in Phase 6 section. 
  • M: Remove existing signals at Gloucester Crossing. 
  • M: Set up bypass pump for drainage work at Gloucester Crossing. 
  • M-F: Install 36" drain pipe and associated manholes.