Construction Alert - 5/5/17

Phase 5 (Rantoul St: from Elliott St to Lenox St) – Paving will commence Wednesday May 10 and continue on Friday May 12 and pick-up again the beginning of the week of May 15, weather permitting.  The work will start at Lenox St and move south bound to Elliott Street. 

Phase 6 (Cabot St: Lenox St to Colon St) – Full depth pulverization of the road way will commence on Monday May 8.  This work will last an estimated 4 weeks before paving will take place in this phase.  At most times two lanes of traffic, one in each direction, will be possible.  At certain times detours around Gloucester Crossing may be necessary.