Four week look ahead - 

Week of 5/1-5/5:

  • M: Install light foundations and conduit at Elliott St.
  • M-Th: Reset curb on Elliott St. 
  • Tue-F: Grade sidewalks and driveways on Elliott Street.
  • Tue-Th: Test pit on electric lines at Gloucester Crossing.
  • M-F: Plant tree along Phases 1, 2 and 3. 
  • M-Tue: Repair sprinklers and plant sod at Odell Park.
  • M-F: Roadway excavation in Phase 5 section.
  • Tue-Th: Install signal and light conduit crossings in Phase 5 section.  
  • Th: Lower manholes and water gate boxes in Phase 6 section.

Week of 5/8-5/12: 

  • M: Excavate and install new gate foundation at Gloucester Crossing (Subway).
  • M: Remove existing gate and reset with the new gate at Gloucester Crossing (Subway).
  • M: Test pit on water main at Gloucester Crossing.
  • M-F: Grade sidewalks and driveways on Elliott Street.
  • T: Install signal conduit to signal house at Gloucester Crossing.
  • W: Install drainage under relocated duct bank in front of 313-321 Rantoul St. 
  • W: Install PED signal foundation at Gloucester Crossing. 
  • M-Tue: Fine grade for paving in Phase 5 section. 
  • W-F: Pave base and binder in Phase 5 section. 
  • Tue-W: Pulverize roadway in Phase 6 section.
  • Th-F: Roadway excavation in Phase 6 section. 

Week of 5/15-5/19:

  • M: Grade sidewalks and driveways on Elliott Street.
  • W: Assemble light at Windover property. 
  • M: Excavate sidewalks in Phase 5 section. 
  • M-Th: Excavate and pour mast arm foundations in Phase 5 section. 
  • M-F: Install light foundations and conduit in Phase 5 section. 
  • M-F: Roadway excavation in Phase 6 section. 

Week of 5/22-5/26:

  • M-F: Install light foundations and conduit in Phase 5 section. 
  • M-F: Roadway excavation in Phase 6 section.