Project Update - 5/25/17

Four week look ahead - 

Week of 5/29-6/2:

  • Tue: Install drainage under relocated duct bank at 313-321 Rantoul St.
  • M-F: Grade sidewalks at 131 Rantoul St. 
  • M-F: Form and pour sidewalks on Elliott Street.
  • M-F: Plant tree along Phases 1, 2 and 3. 
  • M-W: Install light foundations and conduit in Phase 5 section.
  • M-Th: Install curb on Rantoul St from Chestnut St to Lenox St.
  • Th-F: Install light and signal conduit and foundations lower section of Phase 5. 
  • Tue-F: Grade sidewalks and driveways in Phase 5 section. 
  • Tue-F: Fine grade and pave base and binder in Phase 6 section. 
  • W-F: Roadway excavation and install gravel in Phase 7 section. 

Week of 6/5-6/9: 

  • M-F: Grade sidewalks at 131 Rantoul St. 
  • M: Form and pour sidewalks at 131 Rantoul St.
  • M-F: Assemble and set light poles on Elliott St.
  • M-F: Plant tree along Phases 1, 2 and 3. 
  • M-W: Install light and signal conduit and foundations lower section of Phase 5. 
  • M: Fine grade and pave base and binder in Phase 6 section. 
  • Th-F: Install curb on Rantoul St at Elliott St intersection.
  • M-F: Grade sidewalks and driveways in Phase 5 section. 
  • Tue-F: Excavate sidewalks in Phase 6 section.
  • Th-F: Install light conduit in Phase 6 section.
  • Th-F: Excavate and pour mast arm foundations in Phase 6 section.
  • M-F: Roadway excavation and install gravel in Phase 7 section.  

Week of 6/12-6/16:

  • M-F: Grade sidewalks at 131 Rantoul St. 
  • M-F: Plant tree along Phases 1, 2 and 3. 
  • M: Install curb on Rantoul St at Elliott St intersection.
  • M-F: Grade sidewalks and driveways in Phase 5 section. 
  • Th-F: Install signal wire and set mast arms in Phase 5 area. 
  • Tue-F: Pour sidewalks and driveways in Phase 5 section.
  • M: Excavate sidewalks in Phase 6 section.
  • M-F: Install light conduit in Phase 6 section.
  • M-W: Excavate and pour mast arm foundations in Phase 6 section.
  • M-F: Roadway excavation and install gravel in Phase 7 section. 

Week of 6/19-6/23:

  • M: Grade sidewalks at 131 Rantoul St.  
  • M-W: Install signal wire and set mast arms in Phase 5 area. 
  • M-F: Grade sidewalks and driveways in Phase 5 section. 
  • M-F: Pour sidewalks and driveways in Phase 5 section.
  • M-W: Install light conduit in Phase 6 section.
  • M-F: Install curb in Phase 6 section. 
  • M-Tue: Roadway excavation and install gravel in Phase 7 section.