Four week look ahead - 

Week of 4/10-4/14:

  • M-F: Excavate sidewalks and drives on Elliott Street. 
  • M-Tue: Install drainage Federal St to Creek St. 
  • Tue-F: Install fire hydrants.
  • M-F: Assemble lights and set on foundations in Phases 2, 3 and 4.
  • M-F: Rebuild Verizon manholes and plate below grade in Phase 5 section. 
  • M-Tue: Pulverize roadway in Phase 5 section. 
  • W-F: Roadway excavation in Phase 5 section. 
  • Thu-F: Test pit on electric lines at Gloucester Crossing.

Week of 4/17-4/21: 

  • M-Th: Install fire hydrants.
  • Tue: Test pit on water main at Gloucester Crossing.
  • M: Test pit on electric lines at Gloucester Crossing.
  • M-F: Install light foundations and conduit at Elliott Street.  
  • M-F: Plant trees Phase 1, 2 and 3.
  • M-F: Install loam at Odell Park.   
  • M-F: Roadway excavation in Phase 5 section. 
  • M-Tue: Install signal and light conduit crossings in Phase 5 section.  
  • M-F: Rebuild Verizon manholes and plate below grade in Phase 6 section.
  • M-W: Lower electric manholes in Phase 6 section. 

Week of 4/24-4/28:

  • M-F: Install light foundations and conduit at Elliott Street.  
  • M-F: Plant trees Phase 1, 2 and 3.
  • M-F: Install loam at Odell Park.   
  • M-F: Repair sprinklers and plant sod at Odell Park.
  • M-F: Roadway excavation in Phase 5 section. 
  • M-F: Rebuild Verizon manholes and plate below grade in Phase 6 section.

Week of 5/1-5/5:

  • M-W: Reset curb on Elliott Street.  
  • Tue-F: Grade sidewalks and driveways on Elliott Street.
  • M-F: Repair sprinklers and plant sod at Odell Park.
  • M-F: Roadway excavation in Phase 5 section. 
  • M-F: Rebuild Verizon manholes and plate below grade in Phase 6 section.