Project Update 4/12/17

Four week look ahead - 

Week of 4/17-4/21:

  • M: Excavate sidewalks and drives on Elliott Street. 
  • M-Th: Install fire hydrants.
  • Tue-F: Install light foundations and conduit at Elliott Street.  
  • M-F: Plant trees Phase 1, 2 and 3.
  • M-F: Install loam at Odell Park.   
  • M-F: Rebuild Verizon manholes and plate below grade in Phase 5 section. 
  • M-W: Lower electric manholes in Phase 6 section. 
  • M-F: Roadway excavation in Phase 5 section. 
  • M-W: Test pit on electric lines at Gloucester Crossing.
  • F: Install drainage under relocated duct bank at 313-321 Rantoul St.
  • F: Install catch basin and temp pimp at Gloucester Crossing. 

Week of 4/24-4/28: 

  • M: Test pit on water main at Gloucester Crossing.
  • M-F: Install light foundations and conduit at Elliott Street.  
  • M-F: Plant trees Phase 1, 2 and 3.
  • M-F: Install loam at Odell Park.   
  • M-F: Repair sprinklers and plant sod at Odell Park.
  • M-F: Roadway excavation in Phase 5 section. 
  • M-W: Install signal and light conduit crossings in Phase 5 section.  

Week of 5/1-5/5:

  • M: Install light foundations and conduit at Elliott Street.
  • M-W: Reset curb on Elliott Street.  
  • Tue-F: Grade sidewalks and driveways on Elliott Street.
  • M-F: Repair sprinklers and plant sod at Odell Park.
  • M-F: Roadway excavation in Phase 5 section. 

Week of 5/8-5/12:

  • M-F: Grade sidewalks and driveways on Elliott Street.
  • M-Tue: Fine grade for paving in Phase 5 section. 
  • Tue-F: Pave base and binder in Phase 5 section. 
  • M-Tue: Lower manholes and water gate boxes in Phase 6 section.