Four week look ahead - 

Week of 3/27-3/31:

  • M-F: Install drainage Federal St to Creek St. 
  • M-F: Assemble lights and set on foundations in Phases 2, 3 and 4.
  • M-F: Rebuild Verizon manholes and plate below grade in Phase 5 section. 

Week of 4/3-4/7: 

  • M-F: Excavate for cable and install able at Kittridge Crossing.
  • M-W: Install drainage Federal St to Creek St. 
  • M-F: Assemble lights and set on foundations in Phases 2, 3 and 4.
  • M-F: Excavate sidewalks and drives on Elliott Street. 
  • M-W: Lower mainholes and water gate boxes in Phase 5 section.  
  • Th-F: Install fire hydrants.
  • Th-F: Paint crosswalks and stop bars at Railroad Ave.
  • Th-F: Switch signals from flash at Railroad Ave.  

Week of 4/10-4/14:

  • M-F: Cable connections at Kittridge Crossing. 
  • M-F: Assemble lights and set on foundations in Phases 2, 3 and 4.
  • M-F: Install light foundations and conduit at Elliott Street.  
  • M-F: Install fire hydrants.
  • M-F: Paint crosswalks and stop bars at Railroad Ave.
  • M-F: Switch signals from flash at Railroad Ave.  
  • M-Tue: Pulverize Phase 5B. 
  • W-F: Roadway excavation in Phase 5 section. 

Week of 4/17-4/21:

  • M-F: Install light foundations and conduit at Elliott Street.  
  • M: Install fire hydrants.
  • M: Paint crosswalks and stop bars at Railroad Ave.
  • M: Switch signals from flash at Railroad Ave.
  • M-F: Plant trees Phase 1, 2 and 3.
  • M-F: Install loam at Odell Park.   
  • M-F: Roadway excavation in Phase 5 section.
  • M-Tue: Install signal and light conduit crossings in Phase 5 section.