Project Update - 9/15/16

Four week look ahead - 

Week of 9/12-9/16:

  • W-F: Subgrade slopes and install loam in Phase 1 area.
  • F: Install plants at culvert at intersection of Cabot St and Herrick St. 
  • M-F: Excavate and grade sidewalks in Phase 2 area. 
  • M-F: Pour sidewalks and driveways in the Phase 2 area.
  • Tue-F: Grade and pave binder at driveways in Phase 2 area. 
  • M-F: Install light and signal conduit, handholes and light bases in Phase 3 area.
  • M-F: Roadway excavation and install gravel in Phase 4A area.
  • W-F: Install light and signal conduit street crossings in Phase 4A area. 

Week of 9/19-9/23: 

  • M-Tue: Subgrade slopes and install loam in Phase 1 area.
  • M-Tue: Grade and pave binder at driveways in Phase 2 area.
  • M-Tue: Final adjustments to signals at Beckford St.
  • W: Paint temporary striping in Phase 2 area.
  • W-F: Subgrade slopes and install loam in Phase 2 area. 
  • M-F: Install light and signal conduit, handholes and light bases in Phase 3 area.
  • W-Th: Install signal conduit and pedestal foundations in Phase 3 area.
  • M-F: Roadway excavation and install gravel in Phase 4A area.
  • M-W: Install light and signal conduit street crossings in Phase 4A area. 
  • W-F: Fine grade and pave base and binder in Phase 4A area. 

Week of 9/26-9/30:

  • M: Seed loam areas in Phase 1 & 2 areas.
  • M-Tue: Pave top on driveways in Phase 2 area.
  • M-F: Install light and signal conduit, handholes and light bases in Phase 3 area.
  • M-Th: Pour mast arm foundations at School St. 
  • M-F: Install curb in Phase 3 area.
  • Tue-F: Grade sidewalks and driveways in Phase 3 area. 
  • M-W: Install drainage in Phase 4 area.
  • Th-F: Install hydrant at 31 Elliott St. 
  • M-F: Excavate sidewalks and remove curb in Phase 4A area. 

Week of 10/3-10/7:

  • M-F: Install light and signal conduit, handholes and light bases in Phase 3 area.
  • M-F: Install curb in Phase 3 area.
  • M-F: Grade sidewalks and driveways in Phase 3 area. 
  • W-F: Pour sidewalks and driveways in the Phase 3 area.
  • W-F: Pulverize roadway, excavate and install gravel in Phase 4 area.
  • M-F: Install light conduit, handholes and light bases in Phase 4A area.

Week of 10/10-10/14:

  • M-F: Install curb in Phase 3 area.
  • M-F: Grade sidewalks and driveways in Phase 3 area. 
  • M-F: Pour sidewalks and driveways in the Phase 3 area.
  • M-F: Pulverize roadway, excavate and install gravel in Phase 4 area.
  • M-F: Install light conduit, handholes and light bases in Phase 4A area.