Project Update - 8/12/16

Four week look ahead - 

Week of 8/15-8/19:

  • M-F: Excavate and grade sidewalks in Phase 2 area. 
  • M-Tue: Adjust castings in sidewalk.
  • Th-F: Pour sidewalks and driveways in the Phase 2 section.
  • Th-F: Pour mast arm foundations at Colon St.
  • Tue-F: Install light and signal conduit, handholes and light bases in Phase 2 area.
  • M: Excavate to subgrade and install processed reclaimed gravel in Phase 3 area.
  • M: Install light and signal conduit crossings at School St and Fayette St.
  • M-Tue: Fine grade for paving in Phase 3 area.
  • W-Th: Pave base and binder in Phase 3 area.
  • F: Excavate pavement in sidewalks in Phase 3 area.

Week of 8/22-8/26: 

  • M-F: Excavate, grade sidewalks and install gravel in Phase 2 area. 
  • M-F: Pour sidewalks and driveways in the Phase 2 section.
  • M-W: Install light and signal conduit, handholes and light bases in Phase 2 area.
  • Tue-F: Install curb in Phase 2 area.
  • M-F: Excavate pavement in sidewalks in Phase 3 area.
  • M-F: Install light and signal conduit, handholes and light bases in Phase 3 area.
  • M-F: Pour sidewalks and driveways in the Phase 2 section.

Week of 8/29-9/2:

  • M: Pour sidewalks and driveways in the Phase 2 section.
  • M-Th: Excavate, grade sidewalks and install gravel in Phase 2 area. 
  • F: Install catch basin frames and grates in Phase 2 area.
  • F: Pour sidewalks and driveways in the Phase 2 area.
  • M: Excavate pavement in sidewalks in Phase 3 area.
  • M-F: Install light and signal conduit, handholes and light bases in Phase 3 area.
  • M-F: Roadway excavation and install gravel in Phase 4A area.

Week of 9/5-9/9:

  • M: Install catch basin frames and grates in Phase 2 area.
  • M-Th: Pour sidewalks and driveways in the Phase 2 area.
  • F: Paint temporary pavement markings in Phase 2 area.
  • M-F: Install light and signal conduit, handholes and light bases in Phase 3 area.
  • Th-F: Install drainage in Elliott Street. 
  • M-F: Roadway excavation and install gravel in Phase 4A area.