Project Update - 7/14/16

Four week look ahead - 

Week of 7/18-7/22:

  • M-F: Excavate and grade sidewalks in Phase 1 area. 
  • M-Th: Pave binder at driveways.
  • M-F: Pour sidewalks and driveways in the Phase 1 section.
  • M-F: Excavate sidewalks in Phase 2 area. 
  • M-F: Install light and signal conduit, handholes and light bases in Phase 2 area. 
  • M-F: Excavate to subgrade and install processed reclaimed gravel in Phase 3 area.

Week of 7/25-7/29: 

  • M-F: Set mast arms and complete Balch St signalization.
  • M-F: Install light and signal conduit, handholes and light bases in Phase 2 area. 
  • M-F: Install curb in Phase 2 area.
  • M-F: Pour mast arm foundations at Charles and Beckford intersection.
  • M-F: Excavate to subgrade and install processed reclaimed gravel in Phase 3 area.

Week of 8/1-8/5:

  • M-F: Set mast arms and complete Balch St signalization.
  • M-W: Install light and signal conduit, handholes and light bases in Phase 2 area. 
  • M-F: Install curb in Phase 2 area.
  • M-F: Pour mast arm foundations at Charles and Beckford intersection.
  • M-F: Excavate to subgrade and install processed reclaimed gravel in Phase 3 area.

Week of 8/8-8/12:

  • M-F: Excavate to subgrade and install processed reclaimed gravel in Phase 3 area.
  • M-F: Install drainage on Elliott St.