Four week look ahead - 

Week of 6/6-6/10:

  • M: Test pits for drainage on Rantoul St between Elliott St and Cabot Street.
  • Tue-F: Complete drainage on Elliott St and install hydrant. 
  • M-F: Excavate to subgrade and install processed reclaimed gravel in Phase 2 area.
  • M-F: Screen pulverized gravel in Phase 2 area. 
  • M-Tue: Install signal conduit crossings at Charles St intersection.
  • M-F: Excavate and grade sidewalks in Phase 1 area. 
  • M-F: Install curb in the Phase 1 section. 
  • M-W: Verizon to raise telephone manholes to binder grade.
  • Tue-W: National Grid Gas to lower gas main at Cabot St and Herrick St.
  • W-F: Install light conduit, handholes and light bases. 
  • F: National Grid to core electric manholes and install conduit stubs.

Week of 6/13-6/17: 

  • M-F: Excavate to subgrade and install processed reclaimed gravel in Phase 2 area.
  • M-F: Screen pulverized gravel in Phase 2 area. 
  • M: Install light conduit to electric manhole for Load Center #3. 
  • Tue-F: Install signal conduit crossings at Colon St intersection. 
  • M-W: Complete drainage on Elliott St and install hydrant. 
  • Th-F: Install drainage on Rantoul St between Elliott St and Cabot Street.
  • M-F: Excavate and grade sidewalks in Phase 1 area. 
  • M-F: Install curb in the Phase 1 section. 
  • M-W: Excavate and pour mast arm foundations at Balch St intersection.
  • M-W: Adjust water service boxes in sidewalks. 
  • Th-F: Install signal conduit and PED foundations at Balch St intersection.

Week of 6/20-6/24:

  • M-F: Install drainage on Rantoul St between Elliott St and Cabot Street.
  • M-F: Excavate to subgrade and install processed reclaimed gravel in Phase 2 area.
  • M-F: Screen pulverized gravel in Phase 2 area. 
  • M-F: Install railroad signal conduit crossings at Gloucester Crossing (North).
  • M: Excavate and grade sidewalks in Phase 1 area. 
  • M: National Grid Electric to raise electric manholes to binder grade in Phase 1 area.
  • M-Tue: National Grid Gas to raise gas gates to binder grade in Phase 1 area. 
  • M-W: Raise water gates to binder grade in Phase 1 area. 
  • M-F: Form/place sidewalks in the Phase 1 section.

Week of 6/27-7/1:

  • M-W: Install drainage on Rantoul St between Elliott St and Cabot Street.
  • M: Excavate to subgrade and install processed reclaimed gravel in Phase 2 area.
  • M: Screen pulverized gravel in Phase 2 area. 
  • M-F: Form/place sidewalks in the Phase 1 section.