Project Update - 6/23/16

Four week look ahead - 

Week of 6/27-7/1:

  • M-F: Excavate and grade sidewalks in Phase 1 area. 
  • M-F: Verizon to raise telephone manholes to binder grade.
  • Tue-W: Excavate and pour mast arm foundations at Balch St intersection.
  • Th-F: Install signal conduit and pull boxes at Balch St intersection.
  • W-F: Form sidewalks and driveways in the Phase 1 section.
  • M-Tue: National Grid Gas to raise gas gates to binder grade in Phase 1 area. 
  • M-W: Aggregate to fine grade road in Phase 2 area. 
  • W-Th: Aggregate to pave base layer in Phase 2 area. 
  • M-W: Test pits for drainage on Rantoul St between Elliott St and Cabot Street.

Week of 7/4-7/8: 

  • M-Th: Form sidewalks and driveways in the Phase 1 section.
  • Tue-F: Pour sidewalks and driveways in the Phase 1 section.
  • Tue-W: Aggregate to pave binder layer in Phase 2 area. 
  • Th-F: Excavate sidewalks in Phase 2 area. 
  • Th-F: Install light conduit, handholes and light bases in Phase 2 area. 
  • Tue-F: Excavate to subgrade and install processed reclaimed gravel in Phase 3 area.

Week of 7/11-7/15:

  • M-F: Pour sidewalks and driveways in the Phase 1 section.
  • M-Th: Excavate sidewalks in Phase 2 area. 
  • M-F: Install light conduit, handholes and light bases in Phase 2 area. 
  • M-F: Excavate to subgrade and install processed reclaimed gravel in Phase 3 area.

Week of 7/18-7/22:

  • M: Pour sidewalks and driveways in the Phase 1 section.
  • M-W: Install light conduit, handholes and light bases in Phase 2 area. 
  • W-F: Install curb in Phase 2 area.
  • M-F: Excavate to subgrade and install processed reclaimed gravel in Phase 3 area.