Project Update - 5/3/16

Four week look ahead - 

Week of 5/2-5/6:

  • M-F: Install drainage between Gloucester Crossing to Beckford Street.
  • W-F: Loam disturbed area at Herrick Street culvert. Plant shrubs, trees and hydroseed. 
  • M-Th: Excavate to subgrade and install processed reclaimed gravel.
  • M-Th: Screen pulverized gravel. 

Week of 5/9-5/13: 

  • M-F: Install curb in the Phase 1 section. 
  • M-Th: Lower gas gates for pulverizing. 

Week of 5/16-5/20:

  • M-F: Install curb in the Phase 1 section. 
  • M-F: Grade sidewalks in the Phase 1 section.
  • M-Th: Pulverize Phase 2.
  • F: Form/place sidewalks in the Phase 1 section.
  • M-F: Excavate to subgrade and install processed reclaimed gravel.
  • M-F: Screen pulverized gravel.

Week of 5/23-5/27:

  • M-F: Grade sidewalks in the Phase 1 section.
  • M-F: Form/place sidewalks in the Phase 1 section.
  • M-F: Excavate to subgrade and install processed reclaimed gravel.
  • M-F: Screen pulverized gravel.