Project Update - 5/27/16

Phase Updates (subject to weather and field conditions):

Phase 1 

-          Tuesday May 31 - Paving binder coarse starting at 5:00 am through the end of the day
-          Granite curbing will be installed starting on June 6 and will take approximately 2 weeks
-          Sidewalks will be constructed following the completion of the curb installation.
-        Phase 1 should be completed by late July

Phase 2

-          Over the next month the contractor will be grading the road
-          Once grading is complete the base coarse will be paved followed by the binder coarse
-          The goal is to have the curbing and sidewalks completed by the end of August

Phase 3

-          Begin demolition/full depth road work in 4-6 weeks (once they have completed Phase 2)

Phase 4

-          Construction on utilities and drainage continue