Project Update - 4/14/16

Three week look ahead - 

Week of 4/18-4/22:

  • M: Install signal conduit at Balch St and light conduit at Herrick St. 
  • Tue: Install shallow drainage lateral and gutter inlet at Blaine Avenue.
  • Tue: Fix hydrant at Kittredge Street. 
  • W-F: Install drainage between Gloucester Crossing to Beckford Street.
  • W-Thu: Remove and stack curb.
  • W-Thu: Remove stumps.
  • M-F: Excavate to subgrade and install processed reclaimed gravel.
  • M-F: Screen pulverized gravel. 

Week of 4/25-4/29: 

  • M-F: Install drainage between Gloucester Crossing to Beckford Street.
  • M-F: Excavate to subgrade and install processed reclaimed gravel
  • M-F: Screen pulverized gravel

Week of 5/2-5/6:

  • M-Tue: Install drainage between Gloucester Crossing to Beckford Street.
  • M-W: Loam disturbed area at Herrick Street culvert. Plant shrubs, trees and hydroseed. 
  • M-F: Fine grade and pave base.