Project Update - 3/9/16

Four week look ahead - 

Week of 3/14-3/18:

  • M: Relocate 6" water at Mason St
  • Thu-F: Install 12" drainage pipe between drainage manholes at Mason Street 
  • M-F: Construct footings and walls at the culvert at Cabot at Herrick St.

Week of 3/21-3/25:

  • M-Tue: Install 12" drainage pipe between drainage manholes at Mason Street 
  • M-Tue: City of Beverly to install gate valves to new Middle School.  
  •  W-F: Install drainage between Lyman Street and Herrick Street
  • M-F: Construct footings wall sections at the culvert at Cabot at Herrick St.
  • M-F: Comcast conduit installation between Lyman St to Herrick St.
  • M: Excavate and grade for stone wall at Balch St
  • Tue-W: Rebuild stone wall at Balch St

Week of 3/28-4/1:

  • M: Install drainage between Lyman Street and Herrick Street
  • Tue: Install hydrant at Kittredge Street
  • W-Th: Install drainage at culvert at Cabot St/Herrick St 
  • F: Install drainage from Gloucester Crossing to Beckford Street.

    Week of 4/4-4/8:
  • M-F: Install drainage from Gloucester Crossing to Beckford Street.
  • M-W: Lower castings in preparation for road pulverizing