Project Update - 3/30/16

Four week look ahead - 

Week of 4/4-4/8:

  • M: Finish drainage behind utility poles at Herrick Street. 
  • Tue: Install manhole at Blaine Avenue.  
  • M-F: Install drainage between Gloucester Crossing to Beckford Street.
  • M-F: Comcast conduit installation between Gloucester Crossing to Beckford Street.
  • M-W: Comcast conduit installation between Lyman Street to Herrick Street.
  • M-Tue: Lower castings in preparation for road pulverizing. 
  • M-Tue: National Grid Gas to remove valve on gas main at Cabot St and Blaine Ave.
  • M-Thu: Install railroad signal conduit at Kittridge Crossing
  • Thu: Install fence on retaining wall at Herrick Street culvert.
  • F: Rip rap slopes at Herrick Street culvert.
  • F: Relocate pedestal pole at Balch Street and pave temporary sidewalk.
  • F: Remove granite curb in Phase 1 and stack for Phase 2.

Week of 4/11-4/15: 

  • M-F: Install drainage between Gloucester Crossing to Beckford Street.
  • M: Rip rap slopes at Herrick Street culvert.
  • M-W: Pulverize Phase 1
  • Tue-F: Excavate to subgrade and install processed reclaimed gravel
  • Tue-F: Screen pulverized gravel
  • M-F: Comcast conduit installation between Gloucester Crossing to Beckford Street.

Week of 4/18-4/22:

  • M-Th: Install drainage between Gloucester Crossing to Beckford Street.
  • Tue-Thu: Loam disturbed area at Herrick Street culvert. Plant shrubs, trees and hydroseed. 
  • M-F: Excavate to subgrade and install processed reclaimed gravel
  • M-F: Screen pulverized gravel
  • M-W: Install shallow drainage lateral at 496 Cabot Street.
  • M-W: Install signal conduit at Balch Street.
  • Thu: Install light conduit across Herrick Street.

Week of 4/25-4/29:

  • M-W: Excavate to subgrade and install processed reclaimed gravel
  • M-W: Screen pulverized gravel