Project Update - 3/17/16

* To view the project schedule for full depth roadway and sidewalk construction please click  here.

Four week look ahead - 

Week of 3/21-3/25:

  • M-Th: Install 12" drainage pipe between drainage manholes at Mason Street 
  • M-Tue: City of Beverly to install gate valves to new Middle School.  
  • M-F: Comcast conduit installation between Lyman St to Herrick St.
  • M: Excavate and grade for stone wall at Balch St
  • Tue-W: Rebuild stone wall at Balch St
  • F: Install drainage between Lyman Street and Herrick Street
  • M-F: Construct footings and walls at the culvert at Cabot at Herrick St.
  • Tue-F: Test pits for drainage on Elliott St

Week of 3/28-4/1: 

  • M-W: Install drainage between Lyman Street and Herrick Street
  • M: Continue construction at the culvert at Cabot at Herrick St.
  • M: Sawcut for signal conduit and excavations limits for Phase 1
  • M-W: Lower castings in preparation for road pulverizing 
  • W-Th: Install drainage at culvert 
  • Th: Install hydrant at Kittredge St
  • Th-F: Remove granite curb in Phase 1 and stack for Phase 2
  • M-F: Install drainage from Gloucester Crossing to Beckford Street.
  • M-W: National Grid Gas lower gas gates for road pulverizing.   

Week of 4/4-4/8:

  • M-F: Install drainage from Gloucester Crossing to Beckford Street.
  • M-F: Install railroad signal conduit at Kittridge Crossing
  • M-W: Verizon lower castings for road pulverizing.

Week of 4/11-4/15:

  • M-F: Install drainage from Gloucester Crossing to Beckford Street.
  • M-F: Install light conduit between Lyman and retaining wall.