Project Update - 2/25/16

Three week look ahead - 

Week of 2/29-3/4:

  • M-Tue: Install drainage at Kittredge Street
  • W-Thu: Install drainage at Blaine Avenue
  • F: Install 12" drainage pipe between drainage manholes at Mason Street 
  • M-F: Construct footings and walls at the culvert at Cabot at Herrick St.

Week of 3/7-3/11:

  • M-W: Install 12" drainage pipe between drainage manholes at Mason Street 
  • Th: Install 12" drainage pipe between drainage manhole and catch basin at Mason Street
  •  F: Install drainage between Lyman Street and Herrick Street
  • M-F: Construct footings wall sections at the culvert at Cabot at Herrick St.

Week of 3/14-3/18:

  • M-Th: Install drainage between Lyman Street and Herrick Street
  • M-W: Construct footings wall sections at the culvert at Cabot at Herrick St.