Project Update - 12/18/16

Four week look ahead - 

Week of 12/19-12/23:

  • M-F: Install cobble strips between Railroad Ave and Broadway.
  • M-W: Install drainage between Bow St and Wallis St.
  • M-F: Raise water gate boxes in Phases 1, 2, 3 and 4A.
  • Th-F: Install drainage on Cabot St from Gloucester Crossing to Lenox St.   

Week of 12/26-12/30: 

  • M-Tue: Install cobble strips between Railroad Ave and Broadway.
  • Tue-F: Raise water gate boxes in Phases 1, 2, 3 and 4A.
  • Tue-Th: Install drainage on Cabot St from Gloucester Crossing to Lenox St. 
  • Tue: Fill tree pits in Phase 1 and 2.
  • F: Install drainage between Home St and Federal St. 

Week of 1/2-1/6:

  • Tue-F: Install drainage between Home St and Federal St. 

Week of 1/9-1/13:

  • M-Th: Install drainage between Home St and Federal St.