Project Update - 10/26/16

Four week look ahead - 

Week of 10/24-10/28:

  • Tue: Finish installing curb at Herrick St and Colon St island
  • Tue: Hydroseed behind sidewalk at 45 Rantoul St. 
  • Th-F: Set mast arm and ped poles and remove existing poles at School St. 
  • M-F: Pour sidewalks and driveways in the Phase 3 area. Also pave binder at driveways.
  • M-W: Pulverize roadway, excavate and install gravel on Elliott St. 
  • W-Th: Fine grade and pave base and binder on Elliott St. 
  • Tue-F: Grade and pave binder at driveways in Phase 2 area. 
  • M-F: Install light conduit, bases and handholes in Phase 4A area.
  • M-F: Install curb and grade sidewalks and driveways in Phase 4A area. 

Week of 10/31-11/4: 

  • M-Tue: Grade and pour sidewalk at Herrick St.
  • W-Th: Extend railroad signal conduit to back of sidewalk at Colon St.
  • F: Pour sidewalk and island at Colon St.
  • M-Tue: Set mast arm and ped poles and remove existing poles at School St. 
  •  W-Th: Grade sidewalks at School St. 
  • Th-F: Set brick pavers at Goldberg building.
  • M-F: Grade and pour sidewalks and driveways in the Phase 3 area. Also pave binder at driveways.
  • M-Tue: Install light conduit, bases and handholes in Phase 4A area.
  • M-F: Install curb and grade sidewalks and driveways in Phase 4A area. 
  • W: Install drains at Post Office. 

Week of 11/7-11/11:

  • M: Pour sidewalk at Colon St.
  • M-W: Set brick pavers at Goldberg building.
  • M-F: Grade and pour sidewalks and driveways in the Phase 3 area. Also pave binder at driveways.
  • M-F: Grade sidewalks and driveways in Phase 4A area. 
  • M-F: Pour sidewalks and driveways in Phase 4A area. 
  • M-F: Set mast arm and PED poles and remove existing poles at Railroad Ave. 

Week of 11/14-11/18:

  • M-F: Pour sidewalks and driveways in Phase 4A area. 

Week of 11/21-11/25:

  • M-F: Pour sidewalks and driveways in Phase 4A area.