Project Update - 1/4/16

Three week look ahead - 

Week of 1/4-1/8:

  • M-W: Install drainage lateral at Broadway
  • M: Install catch basins at Lyman St 
  • Tue: Install temporary drain to culvert stream
  • W: Install catch basins at Mason St 
  • Th: Install catch basins at Broadway
  • Th: Remove pavement markings and paint new lines at culvert
  • Th: Install barriers, signs, arrow board and drums for traffic shift at culvert (Traffic shift with narrow the road near the culvert up to Herrick St, expect delays and this configuration will be in place for a couple of months.) 
  • F: Install temporary drain to culvert stream
  • F: Install catch basins at Swan St.
  • F: Remove 6" water/hydrants and cap them at Wallis and Bow Sts.
  • M-W: Comcast to relocate conduit between Swan St and Mason St

Week of 1/11-1/15:

  • M-F: Install remainder of drainage at Broadway
  • M-Tue: Install catch basins at Swan St and pipe to drain manhole.
  • W-F: Install drainage pipe, catch basins and manhole at Russell St at railroad tracks.

Week of 1/18-1/22:

  • M-W: Set up dewatering and excavate for wall footing