Project Update - 1/26/16

Four week look ahead - 

Week of 2/1-2/5:

  • M-F: Finish drainage at Broadway
  • M-Tue: Construct footings at the culvert at Cabot at Herrick St.
  • W-F: Construct wall sections at the culvert at Cabot at Herrick St.

Week of 2/8-2/12:

  • M-F: Install drainage from Swan St to approximately 425 Cabot St. 
  • M-F: Construct wall sections at the culvert at Cabot at Herrick St.
  • M-F: Construct footings at the culvert at Cabot at Herrick St.

Week of 2/15-2/19:

  • M-F: Install drainage from 413 Cabot St to Swan St. 
  • M-F: Construct wall sections at the culvert at Cabot at Herrick St.
  • M-F: Construct footings at the culvert at Cabot at Herrick St.

Week of 2/22-2/26:

  • M-W: Install drainage from 413 Cabot St to Swan St. 
  • M-F: Construct wall sections at the culvert at Cabot at Herrick St.
  • M-F: Construct footings at the culvert at Cabot at Herrick St.