Project Update - 1/16/16

Four week look ahead - 

Week of 1/18-1/22:

  • M-Th: Excavate and install earth support blocks at the culvert at Cabot at Herrick St.
  • F: Finish drainage at Broadway
  • F: Construct footings at the culvert at Cabot at Herrick St.
  • M-F: Install drainage from Lyman St to Swan St. 

Week of 1/25-1/29:

  • M-Th: Finish drainage at Broadway
  • M-F: Construct footings at the culvert at Cabot at Herrick St.
  • M-F: Install drainage from Lyman St to Swan St. 
  • W-F: Construct retaining walls at the culvert at Cabot at Herrick St.

Week of 2/1-2/5:

  • M: Construct footings at the culvert at Cabot at Herrick St.
  • M-W: Install drainage from Lyman St to Swan St. 
  • M-F: Construct retaining walls at the culvert at Cabot at Herrick St.

Week of 2/8-2/12:

  • M-F: Construct retaining walls at the culvert at Cabot at Herrick St.