Project Update - 12/4/15

Three week look ahead - 

Week of 12/7-12/11:

  • M: Install 12" drainage pipe at Railroad Ave to catch basin
  • Tue: Remove hydrant at Pleasant St
  • W-Th: Install drainage at Pleasant St into structure
  • Tue-F: Dig test pits at Wallis St to Riverside St
  • F: Install hydrant at Pleasant St
  • M-F: Comcast to install conduit from 4-6 Rantoul to Fayette St
  • M-W: Complete drainage work at Balch St
  • Th: Install catch basin and drain line at 449 Cabot St 
  • F: Install CB and 12" drain line at Herrick St culvert
  • M-F: National Grid Electric to install utility poles and relocate overhead wires
  • M-F: City to line sewer pipe at Beckford St area (night work)

Week of 12/14-12/18:

  • M: Dig test pits at Wallis St to Riverside St
  • M-F: Comcast to install conduit from 4-6 Rantoul to Fayette St
  • M: Install CB and 12" drain line at Herrick St culvert
  • M-W: City to line sewer pipe at Beckford St area (night work)
  • M-Th: Install drainage at Railroad Ave
  • M-F: National Grid Electric to install utility poles and relocate overhead 
  • F: Remove and replace hydrant at 45 Rantoul St
  • Tue: Install temporary pipe crossing for dewatering at culvert on Cabot St
  • W-F: Install catch basins, drain line and manhole at Russell St

Week of 12/21-12/25:

  • M: Remove  hydrant at Wallis St
  • M-F: National Grid Electric to relocate overhead wires