Three week look ahead - 

Week of 12/21-12/25:

  • M: Install catch basin at Bow St.
  • Tue: Install hydrant at Bow St
  • W: Remove 6" water line at Bow St and Wallis St 
  • Th: Clean up and pave trenches
  • M-Th: Test pits for drainage
  • M-Th: Comcast to install cable in the conduit from 4-6 Rantoul to Railroad Ave
  • M-Th: National Grid Electric to relocate overhead wires
  • M-W: Install drainage pipe, catch basins and manhole at Russell St
  • Tue-Th: City to relocate Comcast conduit

Week of 12/28-1/1:

  • M-W: Install drainage at Pleasant St
  • M-Th: City to relocate Comcast conduit
  • M-Th: Install drainage from Herrick St to Mason St
  • Th: Install drainage at Broadway
  • Th: Clean up and pave trenches
  • M-Th: Comcast to install cable in the conduit from 4-6 Rantoul to Railroad Ave
  • M-Th: National Grid Electric to relocate overhead wires

Week of 1/4-1/8:

  • M-F: Install drainage at Broadway
  • M-F: Install drainage from Herrick St to Mason St
  • M-F: Comcast to install cable in the conduit from 4-6 Rantoul to Railroad Ave
  • M-F: National Grid Electric to relocate overhead wires