Project Update - 12/11/15

Three week look ahead - 

Week of 12/14-12/18:

  • M: Install drainage at Pleasant St into existing manhole
  • Tue-Th: Install drainage at Railroad Ave
  • F: Remove and replace hydrant at 45 Rantoul St
  • M-F: Comcast to install conduit from 4-6 Rantoul to Fayette St
  • M: Install gutter inlet, catch basin and 12" drain line at Herrick St culvert
  • Tue: Install temporary pipe crossing for dewatering at culvert on Cabot St
  • M-W: City to line sewer pipe at Beckford St area (night work)
  • W-F: Dig test pits for drainage from Mason St to Herrick St
  • W: Install hydrant at Kittredge St
  • Th: Install hydrant at Balch St
  • F: Remove and replace hydrant at Herrick St

Week of 12/21-12/25:

  • M: Dig test pits for drainage from Mason St to Herrick St
  • M: Remove hydrant at Wallis St
  • Tue-W: Remove and replace hydrant at Bow St
  • Th: Clean up and pave trenches
  • M-Th: Comcast to install cable in the conduit from 4-6 Rantoul to Fayette St
  • M-Th: National Grid Electric to relocate overhead wires
  • M-W: Install drainage pipe, catch basins and manhole at Russell St

Week of 12/28-1/1:

  • M-Th: Install drainage at Broadway
  • M-Th: Test pits for drainage from 413 Cabot St to Mason St
  • M-Th: Comcast to install cable in the conduit from 4-6 Rantoul to Fayette St
  • M-Th: National Grid Electric to relocate overhead wires