Project Update - 11/30/15

Three week look ahead - 

Week of 11/30-12/4:

  • M: Dig test pits at Railroad Ave and Broadway
  • Tue-Th: Install 12" drainage pipe at Railroad Ave
  • F: Install 12" drainage pipe at Railroad Ave to catch basin
  • M-F: Comcast to install conduit from 4-6 Rantoul to School St
  • M-F: National Grid Electric to install utility poles and relocate overhead 
  • M-F: Verizon/White Mountain Cable to install conduit at Balch St 
  • M: Tie drainage into manhole and install new drainage manhole at 463 Cabot St
  • M-Th: Install 12" drainage pipe from 463 Cabot St to 466 Cabot St
  • F: Complete drainage work at Balch St

Week of 12/7-12/11:

  • M: Install 12" drainage pipe at Railroad Ave to catch basin
  • M-Tue: Complete drainage work at Balch St
  • Tue-W: Install drainage at Pleasant St
  • F: Remove existing hydrants at Pleasant St and Wallis St
  • Tue-Th: Test Pits from #415-417 Cabot St to Balch St
  • W: Install Cb and 12" drain line at Balch St
  • Thu-F: Install CB and 12" drain line at Herrick St culvert
  • F: Install CB, drain line and manhole at Russell St
  • M-F: National Grid Electric to install utility poles and relocate overhead 
  • M-F: Comcast to install conduit from 4-6 Rantoul to School St
  • M-F: City to line sewer pipe at Beckford St area (night work)

Week of 12/14-12/18:

  • M-W: Install drainage at Railroad Ave
  • M-Tue: Install CB, drain line and manhole at Russell St
  • Th-F: Install drainage at Pleasant St
  • M-F: Comcast to install conduit from 4-6 Rantoul to School St
  • M-W: City to line sewer pipe at Beckford St area (night work)