Project Update - 11/20/15

Three week look ahead - 

Week of 11/23-11/27:

  • M-Tue: Install 24" drainage pipe approximately 100 feet before and after the intersection of Pleasant St
  • W-F: Install 12" drainage pipe at Railroad Ave to catch basin
  • M-F: Comcast to install conduit from 4-6 Rantoul to School St
  • M-F: National Grid Electric to install utility poles and relocate overhead 
  • M-Tue: Install drainage laterals between Kittredge St and Russell St
  • M-F: Verizon/White Mountain Cable to install conduit at Balch St 
  • W-F: Complete drainage work at Russell St

Week of 11/30-12/4:

  • M: Install 12" drainage pipe at Railroad Ave to catch basin
  • Tue-F: Install drainage at Pleasant St
  • M-Thu:  Complete drainage work at Balch St
  • F: Test Pits from #415-417 Cabot St to Balch St
  • M-F: National Grid Electric to install utility poles and relocate overhead 

Week of 12/7-12/11:

  • M-Thu: Install drainage at Pleasant St
  • M-Thu: Test Pits from #415-417 Cabot St to Balch St
  • M-F: National Grid Electric to install utility poles and relocate overhead