Project Update - 11/12/15

Three week look ahead - 

Week of 11/16-11/20:

  • M: Install catch basin at Fayette St
  • Tue-F: Install 24" drainage pipe approximately 100 feet before and after the intersection of Pleasant St
  • M-F: Test Pits for drainage from Broadway to Federal St
  • M-F: National Grid Electric to install utility poles and relocate overhead 
  • M-Tue: Install drainage across Balch St to catch basin 
  • Tue: National Grid Electric to hold utility pole for drainage at Balch St
  • Wed: Install new catch basin in Balch St
  • Thu-F: Install drainage laterals between Kittredge St and Russell St

Week of 11/23-11/27:

  • M-Tue: Install 24" drainage pipe approximately 100 feet before and after the intersection of Pleasant St
  • W-F: Install 24" drainage pipe around the intersection of Railroad Ave
  • M-F: Complete drainage work at Russell St
  • F:  Complete drainage work at Balch St
  • M-F: Test Pits from #415-417 Cabot St to Balch St
  • M-F: National Grid Electric to install utility poles and relocate overhead 
  • M-F: Verizon/White Mountain Cable to install conduit at Blach St 

Week of 11/30-12/4:

  • M: Install 24" drainage pipe around the intersection of Railroad Ave
  • Tue-F: Install drainage at Pleasant St
  • M-Wed:  Complete drainage work at Balch St