Project Update - 10/29/15

Three week look ahead - 

Week of 11/2-11/6:

  • M-Tue: Install drainage at Fayette St crossings
  • Wed: Install drainage at Edwards St 
  • Th: Install hydrant at School St
  • F: Install hydrant at Edwards St
  • M-F: Comcast to install conduit from 4-6 Rantoul St to School St
  • M-F: National Grid Electric to install utility poles 
  • M-F: Install drainage from #460 Rantoul Street to Blaine Ave
  • M-F: National Grid Gas will be relocating gas lines from Herrick St to 100 feet short of Russell St.

Week of 11/9-11/13:

  • M: Cap existing 6" gates and remove old hydrants at School St and Edward St
  • Tue: Remove and Replace Hydrant in front of 45 Rantoul St
  • W-F: Install drainage from Pleasant St to Railroad Ave
  • M-F: Install drainage from #460 Rantoul Street to Blaine Ave
  • M-F: Test Pits for drainage from Broadway to Federal St
  • M-F: National Grid Gas will be relocating gas lines from Herrick St to 100 feet short of Russell St.
  • M-F: National Grid Electric to install utility poles 

Week of 11/16-11/20:

  • M-Th: Install drainage from Pleasant St to Railroad Ave
  • M-Tue: Install drainage from #460 Rantoul Street to Blaine Ave
  • Wed-F: Install drainage at Balch St
  • M-F: Test Pits from 415-417 Cabot St to 100 ft short of Balch St
  • M-F: National Grid Electric to install utility poles