Project Update - 10/22/15

Three week look ahead - 

Week of 10/26-10/30:

  • M-F: Install drainage from Pleasant St to Fayette St (NB traffic to be detoured at Cabot St)
  • M-Tues: Install drainage from Russell St to the Memorial School (502 Cabot St) 
  • Tues: Clear trees at Cabot/Herrick St culvert
  • Wed: Install erosion control at Cabot/Herrick St culvert
  • W-Th: Test Pits for drainage from Lyman St to Balch St
  • F: Install drainage from #463 Rantoul Street to 150 feet past Russell St
  • M-F: National Grid Gas will be relocating gas lines near Dairy Queen and Balch St.
  • Wed: National Grid Electric may install a new pole at Balch St and Cabot St. 

Week of 11/2-11/6:

  • M-F: Install drainage from Pleasant St to Fayette St
  • M-F: Install drainage from #463 Rantoul Street to 150 feet past Russell St
  • M-F: Comcast to install conduit from 4-6 Rantoul St to School St

Week of 11/9-11/13:

  • M: Install hydrant at School St
  • Tue: Install hydrant at Edwards St
  • Wed: Cap existing 6" gates and remove old hydrants at School St and Edward St
  • Th: Remove and Replace Hydrant in front of 45 Rantoul St
  • M-F: Install drainage from #463 Rantoul Street to 150 feet past Russell Street