Project Update - 10/19/15

Three week look ahead - 

Week of 10/19-10/23:

  • M-F: Install drainage from Pleasant St to Fayette St
  • M-Tue: Install catch basins from Kittredge St to 150 ft past Blaine Ave. 
  • M: Install hydrant at School St
  • Tue: Install hydrant at Edwards St
  • Wed: Remove old hydrants at School St and Edwards St
  • Thu: Remove and Reset Hydrant in front of 45 Rantoul St
  • F: Pave water and drainage trenches 

Week of 10/26-10/30:

  • M-F: Install drainage from Pleasant St to Fayette St
  • M-F: Install drainage from Russell St to the Memorial School (502 Cabot St) 
  • M-Tue: Clear trees at Cabot/Herrick St culvert
  • Wed: Install erosion control at Cabot/Herrick St culvert

Week of 11/2-11/4:

  • M-Wed: Comcast to install conduit from 4-6 Rantoul St to School St