Construction Update - 9/22/14

National Grid Gas Update:

This is the plan for the remaining work on the current phase of Cabot St. The crew will be working from 8:30 am - 2:00 pm.  

Monday 9/22 - Main connection at Cabot St and Colon St. They will be closing down southbound lane on Cabot St and detour cars down Beckford. They will have the additional police detail at Beckford @ Elliott to help with traffic. If all goes well today this will be their last day out there for this Phase..