Construction Update - 4/7/14

This past week (March 31st-April 4th) National Grid was able to complete several more service tie-ins.  

National Grid's two week look ahead for Phase 1 is:

Week of April 7th-April 11th - Only a few more services remain but there are still approximately 15 main connections remaining. Possible main connections at the intersections of Rantoul at Bow St and Rantoul at Home St.

Week of April 14th-April 18th - Tie in any remaining accessible services between Broadway and Elliott Street. Possible main connections at the intersections of Rantoul at Federal St, Federal at Park St and Rantoul at Riverside St.

Please check back frequently, as we will provide updates when we get them.