Construction Update - 4/25/14

This past week (April 21st - April 25th) National Grid was able to complete all service tie-ins and several more main connections. If all goes well, National Grid could potentially be complete with Phase 1 by the end of next week. 

Today, April 25th, is the last day with 2 crews. The crews are doing test holes on Phase 2 today. One crew on Rantoul St and one on Elliott St.

National Grid's remaining Phase 1 look ahead is:

Week of April 28th - May 2nd  – *Monday April 28th - Main Connection at Pond St @ Rantoul St.* Main connections at the intersections of Federal @ Park St and Rantoul St @ Elliott St.

Please check back frequently, as we will provide updates when we get them.